PHX Datacenter Outage
IdentifiedWe have received significant positive progress from the Phoenix datacenter. A third primary chiller has been successfully restored, and facility temperatures are continuing to stabilize. On-site datacenter staff are actively conducting all-hands physical inspections across core hardware and support infrastructure. Network connectivity to our cabinets appears to have been restored. While we awai...
ELK Datacenter Outage
MonitoringAll networking at this time has been restored, and we are seeing connectivity being re-established for all affected client machines. NetOps determined that the issue was a WAN routing outage with failover not propagating. We are investigating exactly why the failover has not worked and how to prevent this from occurring in the future. While we investigate, we will route all traffic to the failo...